Daily Area-wise, Mine-wise, Technology-wise Production For : 20-Jul-2012
Area: KGM
    Daily Monthly Yearly Last Year
Mine Tech Target Actual %Achv Target Actual %Achv Target Actual %Achv
PVK-5 LH912 1546 1200 78 26285 18660 71 145385 101230 70 51024
 
VK 7 INC LH912 988 500 51 16804 16360 97 92904 88662 95 47587
  CM 1396 700 50 23735 17965 76 131335 129472 99 87220
 
  MISC., 0 83 NA 0 945 NA 0 10100 NA 14786
Mine Total 2384 1283 54 40539 35270 87 224239 228234 102 149593
GK OC SHV 9038 2620 29 153654 148166 96 893654 719382 80 708499
 
JVR OC SHV 9615 8673 90 163462 222396 136 933462 1133917 121 1118419
 
Total 22583 13776 61 383940 424492 111 2196740 2182763 99 2027535
Area: YLD
    Daily Monthly Yearly Last Year
Mine Tech Target Actual %Achv Target Actual %Achv Target Actual %Achv
21 INC LH811 0 0 NA 6674 6951 104 36974 35315 96 33887
  BG1 0 0 NA 15111 12452 82 83111 57263 69 74966
Mine Total 0 NA NA 21785 19403 89 120085 92578 77 108853
JK OC SHV 0 0 NA 75556 54000 71 375556 249840 67 200340
 
KOYAGUDEM OC-II SHV 0 5205 NA 94444 190607 202 564444 834375 148 909843
 
Total 0 5205 NA 191785 264010 138 1060085 1176793 111 1219036
Area: MNG
    Daily Monthly Yearly Last Year
Mine Tech Target Actual %Achv Target Actual %Achv Target Actual %Achv
PK 1 INC HS 0 45 NA 0 1163 NA 0 4375 NA 14122
  SDL 442 470 106 7519 8136 108 41719 41751 100 29641
Mine Total 442 515 117 7519 9299 124 41719 46126 111 43763
PK OC SHV 19577 7075 36 332808 421703 127 2078808 2187412 105 2018509
 
KONDAPURAM SDL NA 0 NA NA 0 NA 0 435 NA 1541
 
Total 20019 7590 38 340327 431002 127 2120527 2233973 105 2063813